Calverton Lane and Roundabout Opening

Thu 13 Aug 2020 - posted by Melanie Hyde

Milton Keynes Council have advised us that on Friday 14th August 2020 Calverton Lane and the Roundabout at the H3/H4 will be opened to traffic. Works will be completed on the road but there will still be presence on site for some off carriageway works such as footway surfacing and street light connection works.

Watling Street from the H3 Monks Way to H4 Dansteed Way will still be closed until the underpass works are completed, they are working towards an opening date of 28th August for the full length of Watling Street.

Additionally please note that Calverton Lane will be closed at Upper Weald for 3 days from the 18th August – 20th August for water main connection works.